Schedule

1. Design

Find the best granny flat solution for your land

2. Approval

Get approval for your construction and Loan

3. Construction

10 weeks to completion. Details each week as outlined below.

WEEK 1
Site Establishment

WEEK 2 
Form and pour concrete slab
Termite Protection

WEEK 3 
Timber wall & roof framing
Window Installation

WEEK 4 
Roof and Façade

WEEK 5 
Internal Plumbing Electrical rough-in

WEEK 6
External wall & ceiling insulation
Internal wall plasterboard linings
Waterproofing of wet areas

WEEK 7 
Floor and wall tiling

WEEK 8 
Kitchen Installation
Plumbing fit-out

WEEK 9 
Joineries and painting
Appliances Installed

WEEK 10 
Electrical fit-out and power connection
General touch-up and cleaning
Final Inspection & Occupation Certificate
Handover

Lorem ipsum dolor sit amet.

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat.

Read More

Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam,

Find us on Facebook
Follow us on Twitter

© 2019 Nexthome Granny Flat